What you need to know
If you're planning to install small-scale generation equipment (up to 3.68kW per phase) at multiple properties or multiple generators at a single site, there are important steps you must follow before connecting to our network to ensure compliance with regulations and for a smooth connection process.
When do you need to apply?
You must apply before you connect if:
- You’re installing up to 3.68kW per phase at more than one property
- There is more than one generator at a single property
- Another property within the same postcode (ignoring the last two digits, e.g., PH1 2xx) has had generation installed within the last 28 days by the same installer.
Even if the total generation across all properties or generators is below 3.68kW, an application is still required. We may need to make adjustments to our network to ensure your generation runs correctly.
Application process and timeline
Once we receive all the required information, we will review your application and decide if any network upgrades are needed. It can take up to 45 working days to provide a quote, starting from the date we receive the completed application.
What information do we need?
To process your application, you must complete and submit our application form with the following:
- Property details: Address and Meter Point Administration Number (MPAN) if available
- Generation capacity: The proposed total capacity of the installed generation (kW) for each property
- Inverter Type Test Certificate: The power rating (kW) on the certificate must match the inverter rating shown on the schematic diagram
- Site Plan: A map showing all properties to be connected, with markings indicating which generator is connecting at each property. The map needs to be labelled to match the address details provided on the G98 Form A.
Next steps
You will need to download and complete the G98 - Form A, and attach it alongside our online application form.
Once we have all required information, we will register your project and pass your application to our connection designers for review.

Frequently asked questions
Get in touch
Would you like to speak to us before you apply or have a question about an existing application?