What Generation Connections options are there?

We are committed to protecting the environment and leading the UK in generating energy from wind and water. That’s why we’re here to support you and your installers with all your generation and storage needs. Our helpful pages below will advise on what to do based on your needs. 

Options available:

  • Generation connections below 50KW

    Find out more about how you can connect your small generation project if the storage capacity or generation is less than 50KW.

  • Generation connections over 50KW

    Find out more about how you can connect your generation project if the storage capacity or generation will be over 50KW.

  • G98/G99 Generator requirements

    Find out more about the technical commission and compliance requirements when applying for generation connections.

  • Flexible Connections

    Find out more about our flexible connections and whether this option may suit your connection.

Note for installers

If the proposed generator ie Solar PV Inverter, AC Coupled Batteries, Wind Turbine, Hydro Turbine, CHP unit or any other generating unit(s) that has a capacity of 50kW or less, you generally won’t need to worry about network capacity constraints or reinforcement costs in most areas.  

If it is greater than or equal to 50kW, it would be worth checking our thermal Network Capacity map to understand if there are any constraints in your area. 

Network Maps



For installations that fall
in to this category, you will need to complete a
G99 A1-1 Application in advance of installation so that our Network Planners can conduct a full Network Study and issue you with a quote to connect.

If there are constraints in the area, reinforcement is likely to be required for your connection. Transformers can only handle a certain amount of power, and this applies to both small local ones and larger ones at substations. If an area is already stretched, adding more generation might require upgrading the equipment, which can be very expensive. For more information, please email our Commercial Contract Management Team - commercial.contracts@sse.com 

Frequently asked questions

Get in touch

Would you like to speak to us before you apply or have a question about an existing application? 

Our team is available to help guide you through your generation journey. If you would like to speak to is, we are here Monday to Friday 08:00 – 17:00.

Important NESO Announcement:

NESO has announced it will pause receipt of transmission generation connections applications from the 28th January, until a decision has been on connections reform later this year. This means that we cannot submit Transmission Impact Assessments (TIAs) to the NESO. Please refer to our page below with more information, or alternatively you can sign up to our fortnightly Connections Reform lunch and learn sessions here, where we will cover the pause on the 27th January.